Speaking to The Hindu, Yashwanth Chavan, chief public relations officer of BMRCL, confirmed that the CMRS has issued the obligatory security certification mandatory for passenger providers to start on the brand new route.
Another senior BMRCL official stated that the clearance comes with sure circumstances, which have to be fulfilled earlier than business operations can start. “The CMRS sometimes makes a sequence of observations and proposals throughout inspection. Once we adjust to all of the directives, we are going to submit a compliance report. Only after receiving remaining clearance can passenger operations start,” the official advised The Hindu.
The CMRS inspection, led by A.M. Chowdhary, befell over three days beginning July 22. The evaluation coated all features of security and readiness, together with energy provide techniques, signalling, tracks and viaducts, curves, hearth security measures, passenger data techniques, and facilities on the metro stations.
Will PM Modi launch new line?
While a proper date for the road’s inauguration has not but been finalised, BMRCL is working in the direction of an August 15 launch. “We have knowledgeable each the State and Central governments about receiving security clearance, as per protocol,” one other official stated.
Regarding experiences that Prime Minister Narendra Modi is more likely to attend the inauguration, an official stated it’s topic to his schedule. However, there isn’t any official affirmation of his participation but.
Initially, restricted providers are anticipated, with three driverless trains working at a 20-minute frequency. BMRCL plans to steadily scale as much as full-fledged operations with peak hour frequencies of 5 minutes or much less by March 2026.
Delayed mission
The Yellow Line passes by a number of high-density areas, together with Central Silk Board, HSR Layout, and Electronics City, making it a significant hall for commuters and tech employees within the metropolis. The line was initially scheduled to open in 2021, however missed a number of deadlines, the latest being a revised goal of June 2024.
Delays had been primarily because of problems in procuring rolling inventory. In 2019, BMRCL awarded a ₹1,578-crore contract to Chinese agency CRRC to provide 216 coaches and arrange a producing unit in India. However, CRRC failed to fulfill contractual obligations, severely hampering the mission’s timeline. This led BMRCL to subject a number of warnings and discover invoking a ₹372-crore financial institution assure.
To revive progress, CRRC partnered with Kolkata-based Titagarh Rail Systems Limited. This collaboration allowed deliveries to renew, although at a slower tempo than initially deliberate. So far, BMRCL has acquired three practice units for the Yellow Line. A fourth practice is at the moment present process trials on the Titagarh facility and is anticipated to be shipped by July 28, reaching Bengaluru round August 12.
Published – August 01, 2025 06:40 pm IST